Below the Gate 2022 Civil Engineering solved question paper(forenoon session ) which were held on 12-02-2022. The total number of questions are 65, 10 from aptitude and 55 from Civil Engineering. Question paper is cover in 7 pages and each page have 10 questions. Question on this page from 31 to 40 .
Quick links :
Let’s start
Check Sample of detailed explanation in Question 01 and Question 05, So register today without any fee, unlock many feature and content for free. Sign up
Q 31.
An uncompacted heap of soil has a volume of 10000 m3 and void ratio of 1 . If the soil is compacted to a volume of 7500 m3 , then the corresponding void ratio of the compacted soil is _______ . (round off to one decimal place)
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Sample , So register today without any fee, unlock many feature and content for free. Sign up
Correct option is:
Q 32.
A concentrated vertical load of 3000 KN is applied on a horizontal ground surface. Points P and Q are at depths 1 m and 2 m below the ground, respectively, along the line of application of the load.
Considering the ground to be a linearly elastic, isotopic, semi-infinite medium, the ratio of the increase in vertical stress at P to the increase in vertical stress at Q is +_____ . ( in integer )
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Q 33.
At s site, Static Cone Penetration Test was carried out. The measured point (tip) resistance qc was 1000 KPa at a certain depth. The friction ration (fr) was estimated as 1% at the same depth.
The value of sleeve (side) friction ( in KPa ) at that depth was _____ . (in integer )
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Q 34.
During a particular stage of the growth of a crop, the consumptive use of water is 2.8 mm/day . The amount of water available in the soil is 50 % of the maximum depth of available water in the root zone. Consider the maximum root zone depth of the crop as 80 mm and the irrigation efficiency as 70 % .
The interval between irrigation ( in days ) will be _____. ( round off to the nearest integer )
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Q 35.
The bearing of a survey line is N 31^ {\circ} 17 \,' W . Its azimuth observed from north is ____ deg. ( round off to two decimal places )
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Sample , So register today without any fee, unlock many feature and content for free. Sign up
Correct option is:
Learn more : Previous year Gate papers of Civil Engineering with detailed solution
Learn more : GATE 2022 All branches Aptitude Questions with detailed Solution
Q 36.
The Cartesian coordinates of a point P in a right handed coordinate system are ( 1, 1, 1). The transformed coordinates of P due to a 45 ^{\circ} . clockwise rotation of the coordinate system about the positive x-axis are
[quiz]
[answer] ( 1, 0, \sqrt {2} )
[/answer]
[wrong] ( 1, 0, – \sqrt {2} )
[/wrong]
[wrong] ( -1, 0, \sqrt {2} )
[/wrong]
[wrong] ( -1, 0, – \sqrt {2} )
[/wrong]
[/quiz]
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Q 37.
A semi-circular bar of radius R m, in a vertical plane, is fixed at the end G, as shown in the figure. A horizontal load of magnitude P KN is applied at the end H. The magnitude of the axial force, shear force and bending moment at point Q for \theta = 45^ {\circ} , respectively are
[quiz]
[answer] \dfrac {P} {\sqrt{2}} \; \textrm{KN} , \dfrac {P} {\sqrt{2}} \; \textrm{KN} ,\dfrac {PR} {\sqrt{2}} \; \textrm{KNm}
[/answer]
[wrong] \dfrac {P} {\sqrt{2}} \; \textrm{KN} , \dfrac {P} {\sqrt{2}} \; \textrm{KN} , 0 \; \textrm{KNm}
[/wrong]
[wrong] 0 \; \textrm{KNm} , \dfrac {P} {\sqrt{2}} \; \textrm{KN} ,\dfrac {PR} {\sqrt{2}} \; \textrm{KNm}
[/wrong]
[wrong] \dfrac {P} {\sqrt{2}} \; \textrm{KN} , 0 \; \textrm{KNm} , \dfrac {PR} {\sqrt{2}} \; \textrm{KNm}
[/wrong]
[/quiz]
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Q 38.
A weld is used for joining an angle section ISA 100 \, \textrm{mm} \, \times 100 \,\textrm{mm} \, \times \, 10 \textrm{mm} to a gusset plate of thickness 15 mm to transmit a tensile load. the permissible stress in the angle is 150 MPa and the permissible shear stress on the section through the throat of the fillet weld is 108 MPa . The location of the centroid of the angle is represented by Cyy in the figure, where Cyy = 28.4mm. The area of cross section of the angle is 1903 mm2 . Assuming the effective throat thickness of the weld to be 0.7 times the given weld size, the lengths L1 and L2 ( rounded-off to the nearest integer ) of the weld required to transmit a load equal to the full strength of the tension member are, respectively
[quiz]
[answer] 541 mm and 214 mm
[/answer]
[wrong] 214 mm and 541 mm
[/wrong]
[wrong] 380 mm and 151 mm
[/wrong]
[wrong] 151 mm and 380 mm
[/wrong]
[/quiz]
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Learn more : Gate syllabus for Civil Engineering
Q 39.
The project activities are given in the following table along with duration and dependency.
Activities | Duration (days) | Depends on |
---|---|---|
P | 10 | – |
Q | 12 | – |
R | 5 | P |
S | 10 | Q |
T | 10 | P, Q |
Which one of the following combinations is correct ?
[quiz]
[answer] Total duration of the project = 22 days, Critical path is Q \rightarrow S
[/answer]
[wrong] Total duration of the project = 20 days, Critical path is Q \rightarrow T
[/wrong]
[wrong] Total duration of the project = 22 days, Critical path is P \rightarrow T
[/wrong]
[wrong] Total duration of the project = 20 days, Critical path is P \rightarrow R
[/wrong]
[/quiz]
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
Q 40.
The correct match between the physical states of the soils given in Group I and the governing conditions given In Group II is
Group I | Group II |
---|---|
1. normally consolidated soil | P. Sensitivity > 16 |
2. quick clay | Q. dilation angle = 0 |
3. sand in critical state | R. liquid limit > 50 |
4. clay of high plasticity | S. over consolidation ratio = 1 |
[quiz]
[answer] 1- S, 2 – P, 3 – Q , 4 – R
[/answer]
[wrong] 1 – Q, 2 – S, 3 – P . 4 – R
[/wrong]
[wrong] 1- Q, 2- P, 3 – R, 4 – S
[/wrong]
[wrong] 1-S, 2 – Q, 3 – P, 4 – R
[/wrong]
[/quiz]
Previously Asked in : Gate CE-forenoon season 2022 ||
Detailed Explanation
[popup_anything id=”152″]